Completion Date            
No Major Milestone Forecast Actual Approx. Cost Status/Dependencies 
Phase IA
1 Approval of site plan Sep-05 Nov-05     
2 Council acclamation & approval Jan-06     Rubber stamp
Phase IB
3 Sanitory sewer design submitted, review requested Dec-05 Dec-06   Letter/design drawing sent
4 Sanitory sewer design reviewed & approved for MOE submission to the city Mar-06 Jan-06    Approval granted by the city
5 Cost estimates (Schedule B) for services submitted to the city Jan-06

Jan-06

  Initial submission complete, revision underway
6 Traffic island & signal modification design submitted Jan-06 Jan-06    Design review completed Jan 24
7 Approval of traffic island and signal mods approved Feb-06     3 months lead time at City
8 Site plan agreement discussion initiated Jan-06 Feb-06   Agreement reached on security deposit
9 Sanitory sewer design submitted by MOE Mar-06 Mar-06   Expedited by the city staff
10 Sanitory sewer design approval granted by MOE May-06 Mar-06   Approval received
11

Site plan agreement finalized and signed

May-06     Negotiation & deposit dependent
12 Detail architectural design complete May-06     Step 12 & 13 to progress in tandem
13 Detail structural design complete May-06      
14 Detail electrical design complete May-06      
15 Detail mechanical and plumbing design complete May-06      
16 Detail sprinkler system design complete Jun-06      
17 Site services installation permit initiated Jun-06     Can begin prior to site plan agreement signed, once MOE approval is granted, 50k deposit required by the city
18 Site services installation permit granted Jul-06      
19 Building permit readiness review - PhaseII Jul-06      
Phase II
20 Tender documnet completed & RFQ released - Site services Jul-06       
21 General contractor for site services selected Aug-06      
22 Building permit application submitted Aug-06     Depending on fund raising success
23 Building permit granted Sep-06     8 wks lead time - if no issues found
24 Site services works begins Sep-06     Step 18 dependent
25 Site services works completed Oct-06     Anticipate two months to complete
26 Foundation, structural work execution review Oct-06      
27 RFQ released for general contractor selection Oct-06       
28 General contractor selected - Phase - II Nov-06      
29 Phase II execution begins Nov-06      
Implementation Plan
Date Updated: 21-March-2006