Project Phases

Phase Preliminary Cost Target Start Target End Status
I-A $150,000 IVQ 03 IIQ 05 Complete
I-B $125,000 IIIQ 05 IIQ 06 In progress
II $2,000,000 IIIQ 06 IIQ 07  
III $2,000,000 IIIQ07 IIQ 08  
IV $500,000 IIIQ08 IVQ 08  
Total              $5,000,000    
(includes various development & permits charges of the city)











Phase I-A:       Completion of studies, elevations, floor layout, landscape design, site plan approval
Phase I-B:       Completion of detailed structural, electrical & mechanical design & building permit by the city
Phase II:         Completion of excavation, site services, foundation, and exterior envelope
Phase III:        Completion of interior facility
Phase IV:        Completion of parking, landscape

Note: Phase I-A, Phase I-B, Phase II combined together make overall Phase I - requiring 2.5 M$